Last updated: Tuesday, December 17, 2024.


Construction is substantially complete on the Modified MOVE Culver City Downtown Corridor. Some construction activities, including traffic signal upgrades and installation of bus/bike platforms, will continue into 2025. 

Construction crews applying a red bus lane marking.
Arts District

Work to refresh curb extensions in the Arts District has been delayed due to material shortages. It will take place in early 2025. More information will be provided when the schedule is confirmed.

Construction Impacts

The City is working to minimize dust, noise, and temporary lane closures throughout construction. However, some level of construction impacts are anticipated to occur.

  • Remember: bikes may use full lane. Please remember to share the road and use a full lane to pass.
  • Businesses will remain open and access will be provided during normal business hours.
  • One lane of traffic in each direction will be maintained at all times.
  • Construction crews are using street sweepers and other measures to minimize dust when possible.

For safety, please observe all posted traffic controls, parking restrictions, and detours.

Bike Detours

Shared bus/bike lanes are open for use throughout the corridor.

See a map of alternate bike routes.

Bus Detours

Bus detours ended on November 1, 2024. However, stops at Washington/Cattaraugus will remain closed until mid-February due to ongoing work. Passengers can board the bus at Washington/Helms.